Variance and trend analysis
- Unlike traditional project management methods that evaluate risk and variance and trends in formal meetings, agile incorporates risk analysis and variance and trend analysis into iteration review meetings.
- Risk and variance and trend analysis may be performed in agile using information radiators, like a risk burndown chart, and the use of traditional earned value management (EVM) to measure cost and schedule variance (CV and SV, respectively).
- [Agile Estimating and Planning. Mike Cohn.]
Earned Value Management (EVM)
- EVM or earned value management is a management technique used to evaluate project performance with respect to cost and schedule.
- EVM relies on other common financial metrics like :
- Budget At Completion (BAC), BAC is the total project budget.
- Actual Cost (AC), AC is the actual cost incurred to date.
- Planned Value (PV), PV is the planned value of work at a given time in a project
- Earned Value (EV), EV is value of work actually completed or earned (e.g., you have completed 50% of the project by week 5 of a 15 week $15,000 project = $7,500 EV).
- Cost Variance (CV),
- Schedule Variance (SV),
- Cost Performance Index (CPI),
- Schedule Performance Index (SPI).
- [Agile Estimating and Planning. Mike Cohn.]
Earned Value Management indicators
- Cost Variance (CV) is the difference between what a project has earned to date and cost to date
- CV = EV – AC
- Schedule Variance (SV) is the difference between what a project has earned to date and what it was planned to earn to date
- SV = EV – PV
- CV and SV can be converted into performance indicators of Cost Performance Index (CPI) and Schedule Performance Index (SPI), respectively, and tracked and charted to show progress over time.
- CPI is a ratio that expresses cost performance.
- CPI = EV/AC.
- If CPI > 1, indicates the project is under budget , the project is earning more than spending;
- CPI < 1, indicates the project is over budget
- SPI is a ratio that expresses schedule performance.
- SPI = EV / PV.
- SPI > 1, the project is ahead of schedule
- SPI < 1, the project is behind schedule.
- [Agile Estimating and Planning. Mike Cohn.]
More informations at PMI-ACP exam
PMI-ACP Tools and Techniques flashcards
PMI-ACP Knowledge and Skills flashcards
PMI-ACP Domains and Tasks flashcards
More informations for the Scrum PSD certification here.